Projects (ON GOING)

ADU Al Ain New Campus

Project Name : ADU Al Ain New Campus
Client: Abu Dhabi University Holding Co. (ADUHC)
Client’s Representative : Fortune Properties LLC
Consultant : Khatib & Alami Consultant
Contractor : Tripoli Contracting
Project Commencement Date : 25 / 08 / 2018
Project Original Duration : 18 months (549 days)
Completion Date for Main Building, Side Parking & External Works :    25-Oct-19
Completion Date for Students Center, Backside Parking & Sport Fields :    25-Feb-20